North Airfield Environmental Review Process Timetable

 Mepa Review Process Projeced Timeline Comments 
 MEPA Issued Certificate Detailing Scope of DEIR February 24th Scope Issued
 Developer Prepares DEIR Based on MEPA Scope At least 6 months TBD (August/September) Done
 Public Meeting Prior to Release of DEIR (review technical data) Various times Meetings Held
 DEIR Released March 2024 Released
 30-Day Public Comment Period TBD 
 MEPA Issues Second Certificate – Scope for Final Environmental Impact Report (FEIR) 14 days after close of Comment Period 
 30-Day Public Comment Period TBD Timeline dependent on scope of the certificate
Final MEPA Certificate is Issued  14 days after close of Comment Period